Schedule variance
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that schedule variance (SV) is: ‘…the cost comparison of what has been earned with what was budgeted. It measures the difference in value between the work planned and the work actually accomplished’
Schedule Variance (SV) = Budgeted Cost of Work Performed (BCWP) – Budgeted Cost of Work Scheduled (BCWS)
Or:
SV% = (SV/BCWS) x 100
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Installing solar panels on listed structures.
The current and future global market dynamics of boilers
Significant challenges but adaptation to sustain for longer.
Designing sustainability and performance into buildings
Specifying and selecting sustainable resilient timber products.
Modifying wood to improve resistance to decay and movement.
A last minute, long look for built environment professionals.
The architecture of creative reuse. Book review.
Sustainable development global goals, history in progress?
"Unless we act now, the 2030 Agenda will become an epitaph for a world that might have been."
Mike Kagioglou FCIOB named CIOB President
'Sustainable Development Goals must be focus for construction'
BSRIA training; a look at what's on offer
From energy management to compliance training.
TESP video warns to beware of rogue trainers.
Highlighting the slippery tactics of non-approved providers.
New Building Safety Wiki launched
Boosting awareness and understanding of the new fire safety regime.
New playbook on AI in construction published by CIOB
How to get to grips with, and the best from AI.
Digital Construction Report NBS
BIM, cloud, off-site, immersive tech, AI, twins and sustainability.